SOLAR + STORAGE · ERCOTRed Holly Storage
Red Holly Storage is a 50.0 MW solar + storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Dawson County, Texas.
Queue statusConsented
- PlanningQueued Sep 2018 (completed)
- ConsentedOct 2020 (current stage)
- Construction (not yet reached)
- OperatingTarget May 2028 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 21INR0033
- Grid region
- ERCOT (Texas)
- Developer
- GreenGo Energy
- Connection point (POI)
- tap 345kV 59900 Longdraw - 79641 Farmland
- Location
- Dawson County, Texas
- Technology
- Battery: 50.0 MW · Battery
- Total requested
- 50.0 MW
- Study phase
- SS Completed, FIS Started, IA
- Queue status
- Active
- Entered queue
- 27 September 2018
- Agreement signed
- 19 October 2020
- Proposed online date
- May 2028
Location
Marker shows the centre of Dawson County; the queue data does not give exact sites.
Other requests in Dawson County
- Longview WindOnshore wind · 353 MW · agreement signed
- Red Holly SolarSolar + storage · 260 MW · agreement signed
- Red Holly Storage 1Solar + storage · 50.0 MW · agreement signed
- Fivemile WindOnshore wind · 282 MW · in study
- Mesquite Creek Windpower RepowerOnshore wind · 213 MW · in study
- Green Holly SolarSolar · 414 MW · suspended
- Al Pastor BESSOther · 103 MW · built
- Lamesa Solar B (Phase II) IVORYSolar · 50.0 MW · built
- Blackwater Draw SolarSolar · 152 MW · withdrawn
- Gold Creek SolarSolar · 140 MW · withdrawn
- Atascosa I SolarSolar · 127 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem