SOLAR Β· ERCOTGreen Holly Solar
Green Holly Solar is a 414 MW solar request suspended in the ERCOT interconnection queue, in Dawson County, Texas.
Queue statusPaused / redesign
- PlanningQueued Jul 2018 (current stage)
- ConsentedMay 2020 (not yet reached)
- Construction (not yet reached)
- OperatingTarget May 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 21INR0021
- Grid region
- ERCOT (Texas)
- Developer
- Copenhagen Infrastructure Partners Fund IV
- Connection point (POI)
- tap 345kV 59900 Longdraw - 79641 Farmland
- Location
- Dawson County, Texas
- Technology
- Solar: 414 MW
- Total requested
- 414 MW
- Study phase
- IA and FIS Pending
- Queue status
- Suspended
- Entered queue
- 10 July 2018
- Agreement signed
- 19 May 2020
- Proposed online date
- May 2026
Location
Marker shows the centre of Dawson County; the queue data does not give exact sites.
Other requests in Dawson County
- Longview WindOnshore wind Β· 353 MW Β· agreement signed
- Red Holly SolarSolar + storage Β· 260 MW Β· agreement signed
- Red Holly StorageSolar + storage Β· 50.0 MW Β· agreement signed
- Red Holly Storage 1Solar + storage Β· 50.0 MW Β· agreement signed
- Fivemile WindOnshore wind Β· 282 MW Β· in study
- Mesquite Creek Windpower RepowerOnshore wind Β· 213 MW Β· in study
- Al Pastor BESSOther Β· 103 MW Β· built
- Lamesa Solar B (Phase II) IVORYSolar Β· 50.0 MW Β· built
- Blackwater Draw SolarSolar Β· 152 MW Β· withdrawn
- Gold Creek SolarSolar Β· 140 MW Β· withdrawn
- Atascosa I SolarSolar Β· 127 MW Β· withdrawn