United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

SOLAR Β· ERCOT

Atascosa I Solar

Atascosa I Solar is a 127 MW solar request withdrawn in the ERCOT interconnection queue, in Dawson County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2018 (completed)
  2. Withdrawn / abandonedSep 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
20INR0102
Grid region
ERCOT (Texas)
Developer
Core Solar
Connection point (POI)
tap 138kV 8221 Big Foot - 8203 Pleasant
Location
Dawson County, Texas
Technology
Solar: 127 MW
Total requested
127 MW
Study phase
FIS Complete
Queue status
Withdrawn
Entered queue
6 June 2018
Proposed online date
May 2022
Withdrawn
September 2020

Location

Marker shows the centre of Dawson County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Dawson County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem