United States › Grid › Interconnection queues › Minnesota
GAS · MISOGas project J3465, Isanti County
Gas project J3465, Isanti County is a 211 MW gas request in interconnection study in the MISO interconnection queue, in Isanti County, Minnesota, connecting to GREAT RIVER ENERGY.
Queue statusIn planning
- PlanningQueued Mar 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jun 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J3465
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- GREAT RIVER ENERGY
- Connection point (POI)
- CAMBRIDGE
- Location
- Isanti County, Minnesota
- Technology
- Gas: 211 MW
- Total requested
- 211 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 1
- Queue status
- Active
- Entered queue
- 27 March 2024
- Proposed online date
- June 2026
Location
Marker shows the centre of Isanti County; the queue data does not give exact sites.
Other requests in Isanti County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem