United States › Grid › Interconnection queues › Minnesota

GAS · MISO

Gas project J3465, Isanti County

Gas project J3465, Isanti County is a 211 MW gas request in interconnection study in the MISO interconnection queue, in Isanti County, Minnesota, connecting to GREAT RIVER ENERGY.

Queue statusIn planning
  1. PlanningQueued Mar 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J3465
Grid region
MISO (Midcontinent)
Utility / transmission owner
GREAT RIVER ENERGY
Connection point (POI)
CAMBRIDGE
Location
Isanti County, Minnesota
Technology
Gas: 211 MW
Total requested
211 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 1
Queue status
Active
Entered queue
27 March 2024
Proposed online date
June 2026

Location

Marker shows the centre of Isanti County; the queue data does not give exact sites.

Power plants in Minnesota · Transmission lines in Minnesota

Other requests in Isanti County