Zeus Rusk BESS

Zeus Rusk BESS is a 209 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Rusk County, Texas.

Queue statusIn planning
  1. PlanningQueued Apr 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
25INR0591
Grid region
ERCOT (Texas)
Developer
Rusk BESS, LLC
Connection point (POI)
Tap 345kV 3109 Stryker to 3100 Martin Lake
Location
Rusk County, Texas
Technology
Battery: 209 MW · Battery
Total requested
209 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
9 April 2024
Proposed online date
March 2027

Location

Marker shows the centre of Rusk County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Rusk County