🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

SOLAR + STORAGE · ERCOT

Zeus Rusk Solar

Zeus Rusk Solar is a 26.8 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Rusk County, Texas.

Queue statusIn planning
  1. PlanningQueued Mar 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
25INR0590
Grid region
ERCOT (Texas)
Developer
Rusk Solar, LLC
Connection point (POI)
Tap 345kV 3109 Stryker to 3100 Martin Lake
Location
Rusk County, Texas
Technology
Solar: 26.8 MW · Battery
Total requested
26.8 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
22 March 2024
Proposed online date
March 2027

Location

Marker shows the centre of Rusk County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Rusk County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem