United States βΊ Grid βΊ Interconnection queues βΊ Texas
BATTERY STORAGE Β· ERCOTRailway BESS
Railway BESS is a 255 MW battery storage request suspended in the ERCOT interconnection queue, in Rusk County, Texas.
Queue statusPaused / redesign
- PlanningQueued Jan 2023 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget May 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 25INR0284
- Grid region
- ERCOT (Texas)
- Location
- Rusk County, Texas
- Technology
- Battery: 255 MW
- Total requested
- 255 MW
- Queue status
- Suspended
- Entered queue
- 29 January 2023
- Proposed online date
- May 2026
Location
Marker shows the centre of Rusk County; the queue data does not give exact sites.
Other requests in Rusk County
- Dry Creek Solar ISolar Β· 201 MW Β· agreement signed
- Battery storage project GEN-2020-081, Rusk CountyBattery storage Β· 200 MW Β· agreement signed
- Brantley Branch BattBattery storage Β· 302 MW Β· in study
- Dry Creek Solar IISolar Β· 302 MW Β· in study
- Zeus Rusk BESSSolar + storage Β· 209 MW Β· in study
- Zeus Rusk SolarSolar + storage Β· 26.8 MW Β· in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem