United States › Grid › Interconnection queues › Texas
SOLAR · ERCOTDry Creek Solar I
Dry Creek Solar I is a 201 MW solar request with a signed interconnection agreement in the ERCOT interconnection queue, in Rusk County, Texas.
Queue statusConsented
- PlanningQueued Aug 2021 (completed)
- ConsentedNov 2023 (current stage)
- Construction (not yet reached)
- OperatingTarget Jan 2026 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 23INR0286
- Grid region
- ERCOT (Texas)
- Developer
- OAK HILL SOLAR LLC
- Connection point (POI)
- tap 345kV 3100 Martin Lake - 3105 Elkton (Dorsett 345kV Switching Station)
- Location
- Rusk County, Texas
- Technology
- Solar: 201 MW
- Total requested
- 201 MW
- Study phase
- SS Completed, FIS Completed, IA
- Queue status
- Active
- Entered queue
- 18 August 2021
- Agreement signed
- 2 November 2023
- Proposed online date
- January 2026
Location
Marker shows the centre of Rusk County; the queue data does not give exact sites.
Other requests in Rusk County
- Battery storage project GEN-2020-081, Rusk CountyBattery storage · 200 MW · agreement signed
- Brantley Branch BattBattery storage · 302 MW · in study
- Dry Creek Solar IISolar · 302 MW · in study
- Zeus Rusk BESSSolar + storage · 209 MW · in study
- Zeus Rusk SolarSolar + storage · 26.8 MW · in study
- Railway BESSBattery storage · 255 MW · suspended
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem