🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

SOLAR + STORAGE · ERCOT

Sisters Storage

Sisters Storage is a 209 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Ector County, Texas.

Queue statusIn planning
  1. PlanningQueued Dec 2019 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget May 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
21INR0482
Grid region
ERCOT (Texas)
Developer
174 Power Global Properties
Connection point (POI)
tapping the 345 kV line connecting Moss Switch (Bus# 1018) to Wolf Switching Station (Bus# 11010)
Location
Ector County, Texas
Technology
Battery: 209 MW · Battery
Total requested
209 MW
Study phase
SS Completed, FIS Completed, No IA
Queue status
Active
Entered queue
18 December 2019
Proposed online date
May 2027

Location

Marker shows the centre of Ector County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Ector County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem