United States › Grid › Interconnection queues › Texas

SOLAR + STORAGE · ERCOT

Sisters Solar

Sisters Solar is a 302 MW solar + storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Ector County, Texas.

Queue statusConsented
  1. PlanningQueued Feb 2019 (completed)
  2. ConsentedJul 2025 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget May 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
21INR0265
Grid region
ERCOT (Texas)
Developer
Oberon Solar LLC
Connection point (POI)
tapping the 345 kV line connecting Moss Switch (Bus# 1018) to Wolf Switching Station (Bus# 11010)
Location
Ector County, Texas
Technology
Solar: 302 MW · Battery
Total requested
302 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
28 February 2019
Agreement signed
1 July 2025
Proposed online date
May 2027

Location

Marker shows the centre of Ector County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Ector County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem