United States › Grid › Interconnection queues › Texas

BATTERY STORAGE · ERCOT

Van Zandt Energy Storage

Van Zandt Energy Storage is a 257 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Ector County, Texas.

Queue statusIn planning
  1. PlanningQueued Jun 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Apr 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
25INR0301
Grid region
ERCOT (Texas)
Developer
Rocky Mountain Energy Holdings, LLC
Connection point (POI)
1027 Odessa EHV Switch 138 kV
Location
Ector County, Texas
Technology
Battery: 257 MW
Total requested
257 MW
Study phase
SS Completed, FIS Completed, No IA
Queue status
Active
Entered queue
7 June 2023
Proposed online date
April 2027

Location

Marker shows the centre of Ector County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Ector County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem