Greyhound Solar

Greyhound Solar is a 336 MW solar request with a signed interconnection agreement in the ERCOT interconnection queue, in Ector County, Texas.

Queue statusConsented
  1. PlanningQueued Mar 2019 (completed)
  2. ConsentedJan 2022 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
21INR0268
Grid region
ERCOT (Texas)
Developer
Rockhound Solar 2, LLC dba "Greyhound Solar"
Connection point (POI)
Tap 345kV 11010 Wolf - 1018 Moss
Location
Ector County, Texas
Technology
Solar: 336 MW
Total requested
336 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
28 March 2019
Agreement signed
15 January 2022
Proposed online date
March 2026

Location

Marker shows the centre of Ector County; the queue data does not give exact sites.