BATTERY STORAGE · ERCOTRock Rose BESS
Rock Rose BESS is a 212 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Fort Bend County, Texas.
Queue statusConsented
- PlanningQueued Sep 2023 (completed)
- ConsentedJun 2024 (current stage)
- Construction (not yet reached)
- OperatingTarget Dec 2026 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 26INR0201
- Grid region
- ERCOT (Texas)
- Developer
- Rock Rose Energy Storage LLC
- Connection point (POI)
- 44070 Whaley 345 kV
- Location
- Fort Bend County, Texas
- Technology
- Battery: 212 MW
- Total requested
- 212 MW
- Study phase
- SS Completed, FIS Completed, IA
- Queue status
- Active
- Entered queue
- 22 September 2023
- Agreement signed
- 15 June 2024
- Proposed online date
- December 2026
Location
Marker shows the centre of Fort Bend County; the queue data does not give exact sites.
Other requests in Fort Bend County
- Avalon BESSBattery storage · 522 MW · agreement signed
- Buffalo CreekSolar · 439 MW · agreement signed
- Fighting Jays SolarSolar · 351 MW · agreement signed
- Buffalo Creek BESSBattery storage · 251 MW · agreement signed
- Bypass Battery StorageBattery storage · 208 MW · agreement signed
- Crowned Heron BESS 2Battery storage · 154 MW · agreement signed
- Crowned Heron BESSBattery storage · 154 MW · agreement signed
- IEP Orchard BESSBattery storage · 10.0 MW · agreement signed
- Bypass BESS IIBattery storage · 416 MW · in study
- Unicorn BESSBattery storage · 279 MW · in study
- Elan BESSBattery storage · 203 MW · in study
- Pato Blanco StorageBattery storage · 71.3 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem