BATTERY STORAGE · ERCOT

Crowned Heron BESS 2

Crowned Heron BESS 2 is a 154 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Fort Bend County, Texas.

Queue statusConsented
  1. PlanningQueued Nov 2022 (completed)
  2. ConsentedAug 2024 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
24INR0493
Grid region
ERCOT (Texas)
Developer
RWE Renewables
Connection point (POI)
WA Parish 345 kV Bus #44000
Location
Fort Bend County, Texas
Technology
Battery: 154 MW
Total requested
154 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
23 November 2022
Agreement signed
20 August 2024
Proposed online date
March 2026

Location

Marker shows the centre of Fort Bend County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Fort Bend County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem