BATTERY STORAGE · ERCOT

Bypass Battery Storage

Bypass Battery Storage is a 208 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Fort Bend County, Texas.

Queue statusConsented
  1. PlanningQueued Aug 2021 (completed)
  2. ConsentedDec 2023 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2025 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
23INR0336
Grid region
ERCOT (Texas)
Developer
Bypass BESS LLC
Connection point (POI)
44000 W_A_P__POI5A 345 kV
Location
Fort Bend County, Texas
Technology
Battery: 208 MW
Total requested
208 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
18 August 2021
Agreement signed
4 December 2023
Proposed online date
December 2025

Location

Marker shows the centre of Fort Bend County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Fort Bend County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem