United States › Grid › Interconnection queues › Texas

BATTERY STORAGE · ERCOT

IEP Orchard BESS

IEP Orchard BESS is a 10.0 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Fort Bend County, Texas.

Queue statusConsented
  1. Planning (completed)
  2. ConsentedAug 2023 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
23INR0556
Grid region
ERCOT (Texas)
Developer
IEP Tejas Verde LLC
Connection point (POI)
Station Name (TDSP Station Code): OR Load/Load Transformer Name :TR1 PTI BUS number: 44541 Voltage in kV (Transmission Level): 138 kV Project Size: 9.99 MW battery energy storage (BESS) system; 50 MWh
Location
Fort Bend County, Texas
Technology
Battery: 10.0 MW
Total requested
10.0 MW
Study phase
IA Executed
Queue status
Active
Agreement signed
9 August 2023
Proposed online date
September 2026

Location

Marker shows the centre of Fort Bend County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Fort Bend County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem