🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

SOLAR · ERCOT

Buffalo Creek

Buffalo Creek is a 439 MW solar request with a signed interconnection agreement in the ERCOT interconnection queue, in Fort Bend County, Texas.

Queue statusConsented
  1. PlanningQueued Aug 2019 (completed)
  2. ConsentedApr 2020 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Feb 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
21INR0406
Grid region
ERCOT (Texas)
Developer
Lincoln Clean Energy Development
Connection point (POI)
tap 345kV 44000 WA Parish – 44040 BAILEY
Location
Fort Bend County, Texas
Technology
Solar: 439 MW
Total requested
439 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
1 August 2019
Agreement signed
16 April 2020
Proposed online date
February 2026

Location

Marker shows the centre of Fort Bend County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Fort Bend County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem