🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

BATTERY STORAGE · ERCOT

New Minglewood Energy Center

New Minglewood Energy Center is a 208 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Ward County, Texas.

Queue statusIn planning
  1. PlanningQueued May 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
27INR0255
Grid region
ERCOT (Texas)
Developer
Nova Clean Energy LLC
Connection point (POI)
#11098 Sand Lake Switch Station (SANDLAKE_5) 345kV
Location
Ward County, Texas
Technology
Battery: 208 MW
Total requested
208 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
9 May 2024
Proposed online date
September 2027

Location

Marker shows the centre of Ward County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Ward County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem