Frizzle BESS is a 181 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Ward County, Texas.
Queue statusIn planning
- PlanningQueued Sep 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Oct 2027 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 27INR0562
- Grid region
- ERCOT (Texas)
- Developer
- Frizzle BESS, L.L.C.
- Connection point (POI)
- #38143, TNSLVRLEAF1, 138kV
- Location
- Ward County, Texas
- Technology
- Battery: 181 MW
- Total requested
- 181 MW
- Study phase
- SS Completed, FIS Started, No IA
- Queue status
- Active
- Entered queue
- 11 September 2025
- Proposed online date
- October 2027
Location
Marker shows the centre of Ward County; the queue data does not give exact sites.
Other requests in Ward County
- BasRanch (TEF - Due Diligence)Gas · 1,350 MW · agreement signed
- Vast Sands Power II (TEF-Due Diligence)Gas · 440 MW · agreement signed
- Vast Sands Power I (TEF -Due Diligence)Gas · 440 MW · agreement signed
- Staghorn GasGas · 10.0 MW · agreement signed
- Pyote GasGas · 9.9 MW · agreement signed
- Cedarvale GasGas · 9.9 MW · agreement signed
- New Minglewood Energy CenterBattery storage · 208 MW · in study
- BRP Rhine BESSBattery storage · 207 MW · in study
- BRP Pyxis BESSBattery storage · 207 MW · in study
- Proteus Thornton Ranch Solar SLFSolar + storage · 180 MW · in study
- Shallow Valley StorageBattery storage · 103 MW · in study
- FLIFER Solar ISolar · 84.0 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem