United States › Grid › Interconnection queues › Texas

BATTERY STORAGE · ERCOT

Frizzle BESS

Frizzle BESS is a 181 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Ward County, Texas.

Queue statusIn planning
  1. PlanningQueued Sep 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
27INR0562
Grid region
ERCOT (Texas)
Developer
Frizzle BESS, L.L.C.
Connection point (POI)
#38143, TNSLVRLEAF1, 138kV
Location
Ward County, Texas
Technology
Battery: 181 MW
Total requested
181 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
11 September 2025
Proposed online date
October 2027

Location

Marker shows the centre of Ward County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Ward County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem