BATTERY STORAGE · ERCOT

BRP Rhine BESS

BRP Rhine BESS is a 207 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Ward County, Texas.

Queue statusIn planning
  1. PlanningQueued Aug 2020 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
23INR0075
Grid region
ERCOT (Texas)
Developer
BRP Rhine BESS LLC
Connection point (POI)
Tap 345kV 11188 QUARRYFLD - 11010 WOLF
Location
Ward County, Texas
Technology
Battery: 207 MW
Total requested
207 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
4 August 2020
Proposed online date
December 2028

Location

Marker shows the centre of Ward County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Ward County