United States › Grid › Interconnection queues › Texas

SOLAR · ERCOT

FLIFER Solar I

FLIFER Solar I is a 84.0 MW solar request in interconnection study in the ERCOT interconnection queue, in Ward County, Texas.

Queue statusIn planning
  1. PlanningQueued Mar 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Apr 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
24INR0538
Grid region
ERCOT (Texas)
Developer
FLIFER LLC
Connection point (POI)
Tap 138 kV Yucca Drive Switch (bus# 1009) – Sand Tank (bus# 11197)
Location
Ward County, Texas
Technology
Solar: 84.0 MW
Total requested
84.0 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
8 March 2023
Proposed online date
April 2027

Location

Marker shows the centre of Ward County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Ward County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem