United States › Grid › Interconnection queues › Illinois

SOLAR · PJM

Broomstick Solar Energy Centergy Center

Broomstick Solar Energy Centergy Center is a 210 MW solar request suspended in the PJM interconnection queue, in Christian County, Illinois, connecting to ComEd.

Queue statusPaused / redesign
  1. PlanningQueued Mar 2018 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AD2-100
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
ComEd
Connection point (POI)
Kincaid-Pana 345 kV
Location
Christian County, Illinois
Technology
Solar: 210 MW
Total requested
210 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Suspended
Entered queue
23 March 2018
Proposed online date
December 2028

Location

Marker shows the centre of Christian County; the queue data does not give exact sites.

Power plants in Illinois · Transmission lines in Illinois

Other requests in Christian County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem