Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown9,1872,001.0 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

9,187 requests · page 110 of 184
ProjectCapacityStatusLocationRegionQueuedOnline
Lupinus Storage 2
Solar + storage · Lupinus Solar 2, LLC
125 MWAgreement signed Franklin, TXERCOT Dec 2021target 2027
Replacing 124.4 MW of existing gas generation with solar at Woodruff County (formerly Bailey); Woodruff Co Solar
Other
124 MWIn study MISO Feb 20222024
El Rey Power Bank
Battery storage
124 MWIn study Monterey, CACAISO Apr 2021target 2029
Ajo Power Bank
Battery storage
124 MWAgreement signed Santa Clara, CACAISO Apr 2018target 2028
Backbone Creek BESS
Battery storage · Backbone Creek BESS LLC
124 MWAgreement signed Burnet, TXERCOT Apr 2022target 2026
Gas project GEN-2024-334, Kay County
Gas
124 MWIn study Kay, OKSPP Mar 2025target 2029
Solar + storage project IC-1068, Emanuel County
Solar + storage
124 MWAgreement signed Emanuel, GASoutheast Sep 2022target 2027
Solar project J2187, Laporte County
Solar
124 MWIn study Laporte, INMISO Mar 2022target 2024
EMPower Odessa (TEF - Due Diligence)
Gas · EMPOWER USA, LLC
123 MWIn study Ector, TXERCOT Jul 2024target 2028
Bonita Bateria 2
Battery storage
123 MWIn study Orange, CACAISO Apr 2023target 2029
Sleepy Hollow BESS
Battery storage · Sleepy Hollow BESS, LLC
123 MWIn study Throckmorton, TXERCOT Nov 2023target 2028
Battery storage project ERAS-2025-022, Pontotoc County
Battery storage
123 MWIn study Pontotoc, OKSPP Oct 2025target 2028
Los Esteros Critical Energy Facility Expansion
Gas
123 MWAgreement signed Santa Clara, CACAISO May 2008target 2023
Great Hambino BESS
Battery storage · Atascosa BESS, LLC
123 MWIn study Atascosa, TXERCOT Sep 2025target 2027
Signal Hill BESS I
Battery storage · Signal Hill Generating LLC
123 MWIn study Wichita, TXERCOT Sep 2024target 2027
East West BESS
Battery storage · East West Energy Storage, LLC
123 MWAgreement signed Kerr, TXERCOT Oct 2022target 2027
Prairie Blossom Storage
Battery storage · Prairie Blossom Storage, LLC
123 MWIn study Howard, TXERCOT Dec 2024target 2028
Arnold Hills Storage
Battery storage · Arnold Hills Storage, LLC
123 MWIn study Henderson, TXERCOT Mar 2025target 2029
Dove Wing Storage
Battery storage · Dove Run Solar Project, LLC
122 MWIn study Duval, TXERCOT Feb 2024target 2028
Sayle Solar SLF
Solar + storage · Sayle Solar LLC
122 MWIn study Jackson, TXERCOT Jun 2024target 2027
Morning Glory Solar
Solar · Armadillo Solar, LLC
122 MWIn study Tom Green, TXERCOT Jun 2021target 2026
Sayle Storage SLF
Solar + storage · Sayle Storage LLC
122 MWIn study Jackson, TXERCOT Jun 2024target 2027
Solar project 790, Washington County
Solar
122 MWIn study Washington, IDWest Apr 2025target 2030
Battery storage project S0033, Washington County
Battery storage
122 MWIn study Washington, UTWest Dec 2024target 2027
Grandslam Solar
Solar · Grandslam Solar, L.L.C.
122 MWAgreement signed Atascosa, TXERCOT Jul 2019target 2026
Rock Island Generating (TEF -Due Diligence)
Gas · Kerrville Public Utility Board Public Facility Corporation
122 MWAgreement signed Colorado, TXERCOT Jul 2024target 2027
BRP Ampato BESS
Battery storage · BRP Ampato BESS LLC
122 MWIn study Crane, TXERCOT Aug 2020target 2027
Wildhorse Energy Center
Battery storage
122 MWIn study Sonoma, CACAISO Apr 2021target 2030
Bronc Rodeo Solar Project
Solar · Energiekontor US Texas SP 16 LLC
122 MWIn study Falls, TXERCOT May 2023target 2028
Caney Creek Solar
Solar · HEP Aquamarine Holdings LLC
121 MWAgreement signed Van Zandt, TXERCOT Sep 2020target 2027
Nymphaea Solar
Solar + storage · Nymphaea Solar, LLC
121 MWIn study Wichita, TXERCOT Sep 2022target 2028
Pepper Solar Farm
Solar · Pepper Solar Farm LLC
121 MWAgreement signed Mclennan, TXERCOT Feb 2024target 2027
Dove Run Solar
Solar · Dove Run Solar Project, LLC
121 MWAgreement signed Duval, TXERCOT May 2019target 2027
Marengo BESS
Battery storage · BRP BLUE TOPAZ 8, LLC
121 MWIn study Cameron, TXERCOT May 2023target 2028
Long Point Solar
Solar + storage · Long Point Solar, LLC
121 MWAgreement signed Brazoria, TXERCOT Mar 2017target 2026
Iron Cowboy Solar
Solar + storage · Vaquero II Solar, LLC
121 MWIn study San Patricio, TXERCOT Jun 2025target 2028
High Winds Storage
Battery storage
121 MWIn study Solano, CACAISO Apr 2021target 2031
Sun Cactus Solar
Solar · Sun Cactus Solar Project, LLC
121 MWAgreement signed Duval, TXERCOT Jul 2022target 2027
Wagyu BESS SLF
Battery storage · Wagyu BESS, LLC
121 MWIn study Brazoria, TXERCOT Jun 2025target 2026
Borden Dino Solar
Solar + storage · Borden Dino Solar, LLC
121 MWIn study Borden, TXERCOT Apr 2025target 2028
Neal Battery
Solar + storage · CH Neal Battery LLC
121 MWIn study Wharton, TXERCOT Oct 2025target 2029
Fairway Storage
Battery storage · Fairway Storage LLC
120 MWAgreement signed Freestone, TXERCOT Nov 2022target 2027
Solar project IC-768, Dodge County
Solar
120 MWAgreement signed Dodge, GASoutheast Dec 2018target 2027
Buffalo Gap 1 Wind Repower
Onshore wind · Buffalo Gap Wind Farm, LLC
120 MWAgreement signed Nolan, TXERCOT Jan 2025target 2026
Solar project 558, Jerome County
Solar · Cat Creek Energy, LLC
120 MWAgreement signed Jerome, IDWest May 2019target 2026
Rolling Plains BESS
Battery storage · Haskell County BESS LLC
120 MWIn study Haskell, TXERCOT Aug 2024target 2028
Onshore wind project 715, Uinta County
Onshore wind · Uinta Wind Energy, LLC
120 MWAgreement signed Uinta, WYWest Oct 2015target 2025
AC120SB Project
Solar + storage
120 MWAgreement signed Otero, NMWest Sep 2017target 2022
Battery storage project AI2-230, Caroline County
Battery storage
120 MWIn study Caroline, VAPJM Mar 2023target 2023
Solar project J1389, Saginaw County
Solar
120 MWAgreement signed Saginaw, MIMISO Apr 2019target 2025
Page 110 of 184

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)