United States › Grid › Interconnection queues

OTHER · MISO

Replacing 124.4 MW of existing gas generation with solar at Woodruff County (formerly Bailey); Woodruff Co Solar

Replacing 124.4 MW of existing gas generation with solar at Woodruff County (formerly Bailey); Woodruff Co Solar is a 124 MW other request in interconnection study in the MISO interconnection queue, connecting to ENTERGY ARKANSAS INC..

Queue statusIn planning
  1. PlanningQueued Feb 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingOct 2024 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
R1016
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY ARKANSAS INC.
Connection point (POI)
Bailey 161kV substation(338879)
Technology
Solar: 124 MW · Other
Total requested
124 MW
Service type
Network resource (NRIS)
Queue status
Active
Entered queue
18 February 2022
Proposed online date
May 2023
Came online
October 2024

Location

No county location in the queue data.

Power plants in · Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem