Solar project J1389, Saginaw County

Solar project J1389, Saginaw County is a 120 MW solar request with a signed interconnection agreement in the MISO interconnection queue, in Saginaw County, Michigan, connecting to METC.

Queue statusConsented
  1. PlanningQueued Apr 2019 (completed)
  2. ConsentedJul 2024 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Apr 2025 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
J1389
Grid region
MISO (Midcontinent)
Utility / transmission owner
METC
Connection point (POI)
Murphy Station - Nelson Road 345 kV Line tap
Location
Saginaw County, Michigan
Technology
Solar: 120 MW
Total requested
120 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA Complete; Post GIA Status: Not Started
Queue status
Active
Entered queue
29 April 2019
Agreement signed
1 July 2024
Proposed online date
April 2025

Location

Marker shows the centre of Saginaw County; the queue data does not give exact sites.

Power plants in Michigan · Transmission lines in Michigan

Other requests in Saginaw County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem