🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Michigan

BATTERY STORAGE · MISO

Battery storage project J3438, Saginaw County

Battery storage project J3438, Saginaw County is a 250 MW battery storage request in interconnection study in the MISO interconnection queue, in Saginaw County, Michigan, connecting to METC.

Queue statusIn planning
  1. PlanningQueued Mar 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J3438
Grid region
MISO (Midcontinent)
Utility / transmission owner
METC
Connection point (POI)
MURPHY
Location
Saginaw County, Michigan
Technology
Battery: 250 MW
Total requested
250 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 1
Queue status
Active
Entered queue
26 March 2024
Proposed online date
June 2028

Location

Marker shows the centre of Saginaw County; the queue data does not give exact sites.

Power plants in Michigan · Transmission lines in Michigan

Other requests in Saginaw County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem