United States › Grid › Interconnection queues › Michigan
BATTERY STORAGE · MISOBattery storage project J3656, Saginaw County
Battery storage project J3656, Saginaw County is a 250 MW battery storage request in interconnection study in the MISO interconnection queue, in Saginaw County, Michigan, connecting to ITC.
Queue statusIn planning
- PlanningQueued Mar 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jun 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J3656
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ITC
- Connection point (POI)
- BAUER
- Location
- Saginaw County, Michigan
- Technology
- Battery: 250 MW
- Total requested
- 250 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 1
- Queue status
- Active
- Entered queue
- 26 March 2024
- Proposed online date
- June 2028
Location
Marker shows the centre of Saginaw County; the queue data does not give exact sites.
Other requests in Saginaw County
- Solar project J1389, Saginaw CountySolar · 120 MW · agreement signed
- Solar project J3843, Saginaw CountySolar · 300 MW · in study
- Battery storage project J3438, Saginaw CountyBattery storage · 250 MW · in study
- Solar project J2061, Saginaw CountySolar · 200 MW · in study
- Battery storage project J3782, Saginaw CountyBattery storage · 180 MW · in study
- Onshore wind project J4054, Saginaw CountyOnshore wind · 146 MW · in study
- Solar project J3835, Saginaw CountySolar · 130 MW · in study
- Solar project J1939, Saginaw CountySolar · 125 MW · in study
- Solar project J3124, Saginaw CountySolar · 120 MW · in study
- Battery storage project J3133, Saginaw CountyBattery storage · 120 MW · in study
- Battery storage project E0004, Saginaw CountyBattery storage · 104 MW · in study
- Other project G210 CONS 103, Saginaw CountyOther · 875 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem