United States › Grid › Interconnection queues › Texas
SOLAR + STORAGE · ERCOTSayle Solar SLF
Sayle Solar SLF is a 122 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Jackson County, Texas.
Queue statusIn planning
- PlanningQueued Jun 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget May 2027 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 27INR0251
- Grid region
- ERCOT (Texas)
- Developer
- Sayle Solar LLC
- Connection point (POI)
- Tap 69kV #5522 Edna - #5518 El Toro SW
- Location
- Jackson County, Texas
- Technology
- Solar: 122 MW · Battery
- Total requested
- 122 MW
- Study phase
- SS Completed, FIS Started, No IA
- Queue status
- Active
- Entered queue
- 3 June 2024
- Proposed online date
- May 2027
Location
Marker shows the centre of Jackson County; the queue data does not give exact sites.
Other requests in Jackson County
- New Hickory SolarSolar · 209 MW · agreement signed
- Dios BESSBattery storage · 201 MW · agreement signed
- Third Coast BESSBattery storage · 103 MW · agreement signed
- Sayle Storage SLFSolar + storage · 122 MW · in study
- Texas Sun SolarSolar · 71.7 MW · in study
- KildareSolar · 70.0 MW · in study
- Mustang Creek SolarSolar · 151 MW · built
- Mustang Creek StorageOther · 70.5 MW · built
- Goldenrod Creek SolarSolar · 660 MW · withdrawn
- Lunis Creek Solar 2Solar · 240 MW · withdrawn
- Flag City Storage SLFBattery storage · 169 MW · withdrawn
- Flag City SolarSolar · 166 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem