United States › Grid › Interconnection queues › Texas
BATTERY STORAGE · ERCOTFlag City Storage SLF
Flag City Storage SLF is a 169 MW battery storage request withdrawn in the ERCOT interconnection queue, in Jackson County, Texas.
Queue statusWithdrawn / abandoned
- PlanningQueued Nov 2021 (completed)
- Withdrawn / abandonedDec 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 23INR0414
- Grid region
- ERCOT (Texas)
- Developer
- Flag City Solar Project, LLC
- Connection point (POI)
- tap 138kV 5588 Red Bluff - 5546 Danevang
- Location
- Jackson County, Texas
- Technology
- Battery: 169 MW
- Total requested
- 169 MW
- Study phase
- FIS
- Queue status
- Withdrawn
- Entered queue
- 17 November 2021
- Proposed online date
- December 2027
- Withdrawn
- December 2025
Location
Marker shows the centre of Jackson County; the queue data does not give exact sites.
Other requests in Jackson County
- New Hickory SolarSolar · 209 MW · agreement signed
- Dios BESSBattery storage · 201 MW · agreement signed
- Third Coast BESSBattery storage · 103 MW · agreement signed
- Sayle Solar SLFSolar + storage · 122 MW · in study
- Sayle Storage SLFSolar + storage · 122 MW · in study
- Texas Sun SolarSolar · 71.7 MW · in study
- KildareSolar · 70.0 MW · in study
- Mustang Creek SolarSolar · 151 MW · built
- Mustang Creek StorageOther · 70.5 MW · built
- Goldenrod Creek SolarSolar · 660 MW · withdrawn
- Lunis Creek Solar 2Solar · 240 MW · withdrawn
- Flag City SolarSolar · 166 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem