Texas Sun Solar

Texas Sun Solar is a 71.7 MW solar request in interconnection study in the ERCOT interconnection queue, in Jackson County, Texas.

Queue statusIn planning
  1. PlanningQueued Sep 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
27INR0554
Grid region
ERCOT (Texas)
Developer
Pigg Grounds LLC
Connection point (POI)
Cordele Substation ; Bus no. 5524
Location
Jackson County, Texas
Technology
Solar: 71.7 MW
Total requested
71.7 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
22 September 2025
Proposed online date
December 2027

Location

Marker shows the centre of Jackson County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Jackson County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem