United States › Grid › Interconnection queues › Texas

BATTERY STORAGE · ERCOT

Third Coast BESS

Third Coast BESS is a 103 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Jackson County, Texas.

Queue statusConsented
  1. PlanningQueued Aug 2021 (completed)
  2. ConsentedMay 2023 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
23INR0361
Grid region
ERCOT (Texas)
Developer
Third Coast BESS LLC
Connection point (POI)
8125 Lolita substation 138kV
Location
Jackson County, Texas
Technology
Battery: 103 MW
Total requested
103 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
24 August 2021
Agreement signed
17 May 2023
Proposed online date
June 2027

Location

Marker shows the centre of Jackson County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Jackson County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem