United States › Grid › Interconnection queues › Texas

BATTERY STORAGE · ERCOT

Dios BESS

Dios BESS is a 201 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Jackson County, Texas.

Queue statusConsented
  1. PlanningQueued May 2023 (completed)
  2. ConsentedApr 2025 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
25INR0441
Grid region
ERCOT (Texas)
Developer
Dios BESS, LLC
Connection point (POI)
8117 GANADO138kV
Location
Jackson County, Texas
Technology
Battery: 201 MW
Total requested
201 MW
Study phase
SS Completed, FIS Started, IA
Queue status
Active
Entered queue
15 May 2023
Agreement signed
3 April 2025
Proposed online date
December 2027

Location

Marker shows the centre of Jackson County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Jackson County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem