Sayle Storage SLF

Sayle Storage SLF is a 122 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Jackson County, Texas.

Queue statusIn planning
  1. PlanningQueued Jun 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget May 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
27INR0260
Grid region
ERCOT (Texas)
Developer
Sayle Storage LLC
Connection point (POI)
Tap 69kV #5522 Edna - #5518 El Toro SW
Location
Jackson County, Texas
Technology
Battery: 122 MW · Battery
Total requested
122 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
3 June 2024
Proposed online date
May 2027

Location

Marker shows the centre of Jackson County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Jackson County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem