🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

GAS · ERCOT

Rock Island Generating (TEF -Due Diligence)

Rock Island Generating (TEF -Due Diligence) is a 122 MW gas request with a signed interconnection agreement in the ERCOT interconnection queue, in Colorado County, Texas.

Queue statusConsented
  1. PlanningQueued Jul 2024 (completed)
  2. ConsentedMar 2025 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
27INR0321
Grid region
ERCOT (Texas)
Developer
Kerrville Public Utility Board Public Facility Corporation
Connection point (POI)
57640 Rock Island 138 kV
Location
Colorado County, Texas
Technology
Gas: 122 MW
Total requested
122 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
22 July 2024
Agreement signed
17 March 2025
Proposed online date
June 2027

Location

Marker shows the centre of Colorado County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Colorado County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem