Montezuma Storage

Montezuma Storage is a 185 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Colorado County, Texas.

Queue statusIn planning
  1. PlanningQueued Sep 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
27INR0555
Grid region
ERCOT (Texas)
Developer
Montezuma Storage LLC
Connection point (POI)
L_GLIDDE8_1Y; Bus number - 7258 138KV
Location
Colorado County, Texas
Technology
Battery: 185 MW
Total requested
185 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
22 September 2025
Proposed online date
September 2027

Location

Marker shows the centre of Colorado County; the queue data does not give exact sites.