United States › Grid › Interconnection queues › Texas

SOLAR + STORAGE · ERCOT

Bottom Grass BESS

Bottom Grass BESS is a 202 MW solar + storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Colorado County, Texas.

Queue statusConsented
  1. PlanningQueued Nov 2020 (completed)
  2. ConsentedJun 2023 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2028 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
23INR0083
Grid region
ERCOT (Texas)
Developer
Bottom Grass Solar Project, LLC
Connection point (POI)
tap 345 kV 9073 Holman - 44200 Hillje
Location
Colorado County, Texas
Technology
Battery: 202 MW · Battery
Total requested
202 MW
Study phase
SS Completed, FIS Started, IA
Queue status
Active
Entered queue
5 November 2020
Agreement signed
29 June 2023
Proposed online date
March 2028

Location

Marker shows the centre of Colorado County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Colorado County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem