Paloma Energy Center

Paloma Energy Center is a 194 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Colorado County, Texas.

Queue statusIn planning
  1. PlanningQueued Feb 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
27INR0147
Grid region
ERCOT (Texas)
Developer
Harrison Street Development, LLC
Connection point (POI)
Tap 138 kV 57640 Rock Island - 57639 Sheridan
Location
Colorado County, Texas
Technology
Solar: 194 MW · Battery
Total requested
194 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
7 February 2024
Proposed online date
June 2027

Location

Marker shows the centre of Colorado County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Colorado County