Solar project IC-768, Dodge County

Solar project IC-768, Dodge County is a 120 MW solar request with a signed interconnection agreement in the Southeast interconnection queue, in Dodge County, Georgia, connecting to Southern Company.

Queue statusConsented
  1. PlanningQueued Dec 2018 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jan 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
IC-768
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Bonaire Primary - Eastman Primary 115 kV Line
Location
Dodge County, Georgia
Technology
Solar: 120 MW
Total requested
120 MW
Service type
Energy only (ERIS)
Study phase
IA Executed
Queue status
Active
Entered queue
17 December 2018
Proposed online date
January 2027

Location

Marker shows the centre of Dodge County; the queue data does not give exact sites.