πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Georgia

SOLAR + STORAGE Β· SOUTHEAST

Solar + storage project IC-889, Dodge County

Solar + storage project IC-889, Dodge County is a 30.0 MW solar + storage request withdrawn in the Southeast interconnection queue, in Dodge County, Georgia, connecting to Southern Company.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2020 (completed)
  2. Withdrawn / abandonedApr 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
IC-889
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Bonaire Primary - Eastman Primary 115 kV Line
Location
Dodge County, Georgia
Technology
Solar: 30.0 MW Β· Battery
Total requested
30.0 MW
Service type
Energy only (ERIS)
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
22 July 2020
Proposed online date
July 2023
Withdrawn
April 2024

Location

Marker shows the centre of Dodge County; the queue data does not give exact sites.

Power plants in Georgia Β· Transmission lines in Georgia

Other requests in Dodge County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem