Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown9,1872,001.0 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

9,187 requests · page 109 of 184
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J1203, Genesee County
Solar
125 MWUnder construction Genesee, MIMISO Apr 2019target 2025
Battery storage project GI-2021-145, Riverside County
Battery storage
125 MWIn study Riverside, CAWest Aug 2021target 2027
Solar + storage project IA-PNM-2019-08, Mckinley County
Solar + storage · RWE Solar Dev
125 MWPaused / redesign Mckinley, NMWest Apr 2019target 2022
Solar project AI1-145, Prince Edward County
Solar
125 MWIn study Prince Edward, VAPJM Sep 2022target 2026
Battery storage project LGE-GIS-2023-003, Mercer County
Battery storage
125 MWIn study Mercer, KYSoutheast Apr 2023target 2026
Somerset Solar
Solar · Somerset Solar, LLC
125 MWIn study Niagara, NYNYISO Aug 2020target 2028
Sugar Maple Solar
Solar · Sugar Maple Solar, LLC
125 MWIn study Lewis, NYNYISO Dec 2019target 2027
Solar + storage project GI-2022-163, Riverside County
Solar + storage
125 MWIn study Riverside, CAWest Sep 2022target 2025
Solar project AI1-124, Lunenburg County
Solar
125 MWIn study Lunenburg, VAPJM Sep 2022target 2026
Solar project 588, Ada County
Solar · PVS 2, LLC
125 MWAgreement signed Ada, IDWest Sep 2020target 2026
Solar + storage project GI-TC-2024-21, Montezuma County
Solar + storage
125 MWIn study Montezuma, COWest May 2024target 2028
Battery storage project AH2-084, Fauquier County
Battery storage
125 MWIn study Fauquier, VAPJM Jan 2022target 2027
Battery storage project J1358, Laporte County
Battery storage
125 MWAgreement signed Laporte, INMISO Apr 2019target 2026
Vinton Solar
Solar
125 MWAgreement signed Vinton, OHPJM Oct 2016target 2027
Solar + storage project 2024-G2, Shasta County
Solar + storage
125 MWIn study Shasta, CAWest Nov 2024target 2028
Quarter Horse Solar
Solar · Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
125 MWAgreement signed Charlotte, VAPJM Sep 2020target 2031
Bluestem Solar
Solar · RWE Solar Development, LLC
125 MWIn study Laporte, INPJM Sep 2020target 2023
Solar project J2490, Tuscola County
Solar
125 MWIn study Tuscola, MIMISO Sep 2022target 2025
Onshore wind project GEN-2018-069, Wibaux County
Onshore wind
125 MWAgreement signed Wibaux, MTSPP Oct 2018target 2031
East Setauket Energy Storage
Battery storage · East Setauket Energy Storage, LLC
125 MWIn study Suffolk, NYNYISO Jan 2020target 2027
Saddle Mountain Solar
Solar
125 MWAgreement signed Maricopa, AZCAISO Apr 2020target 2025
Solar project J1310, Jackson County
Solar
125 MWUnder construction Jackson, MIMISO Apr 2019target 2024
Solar + storage project 469, Henderson County
Solar + storage
125 MWAgreement signed Henderson, TNSoutheast Mar 2021target 2028
Bluestem Solar
Solar
125 MWAgreement signed Laporte, INPJM Mar 2020target 2027
Battery storage project Company JP, Washoe County
Battery storage
125 MWAgreement signed Washoe, NVWest Sep 2018target 2027
Solar + storage project J2826, Greene County
Solar + storage
125 MWIn study Greene, INMISO Sep 2022target 2027
Solar + storage project GEN-2023-092, Choctaw County
Solar + storage
125 MWIn study Choctaw, OKSPP Oct 2023target 2028
Solar + storage project Company JE, Churchill County
Solar + storage
125 MWAgreement signed Churchill, NVWest Sep 2018target 2027
Solar project C2-167, Emery County
Solar · PacifiCorp
125 MWIn study Emery, UTWest May 2022target 2026
Battery storage project 21-11157, Larimer County
Battery storage
125 MWIn study Larimer, COWest Nov 2021target 2026
Other project GEN-2025-SR15, Mcclain County
Other
125 MWIn study Mcclain, OKSPP May 2025target 2029
Southern Virginia Solar
Solar
125 MWAgreement signed Pittsylvania, VAPJM Jul 2019target 2027
TOCE GA 1 Solar
Solar
125 MWIn study Burke, GASoutheast Aug 2023target 2026
Solar project J2881, Jefferson County
Solar
125 MWIn study Jefferson, ARMISO Sep 2022target 2026
Battery storage project Q423, Navajo County
Battery storage
125 MWIn study Navajo, AZWest Sep 2021target 2025
Solar project J1620, Pipestone County
Solar
125 MWIn study Pipestone, MNMISO Apr 2024target 2026
Battery storage project 121, King County
Battery storage
125 MWPaused / redesign King, WAWest Aug 2021target 2030
Baldy Mesa 2
Solar + storage
125 MWAgreement signed San Bernardino, CACAISO Apr 2018target 2026
Solar project J1679, Clay County
Solar
125 MWIn study Clay, ILMISO Jun 2020target 2026
Battery storage project Q384, Maricopa County
Battery storage
125 MWPaused / redesign Maricopa, AZWest Mar 2021target 2025
Solar project J2751, Bolivar County
Solar
125 MWIn study Bolivar, MSMISO Sep 2022target 2026
Solar project J857, Calhoun County
Solar
125 MWUnder construction Calhoun, MIMISO Jun 2017target 2022
Battery storage project GEN-2024-251, Eddy County
Battery storage
125 MWIn study Eddy, NMSPP Mar 2025target 2029
Solar project J2384, Shelby County
Solar
125 MWIn study Shelby, ILMISO Sep 2022target 2024
Solar project J3792, Gratiot County
Solar
125 MWIn study Gratiot, MIMISO Apr 2024target 2028
Journey Solar
Solar · Journey Solar, LLC
125 MWIn study Haskell, TXERCOT Mar 2024target 2027
Solar project GEN-2017-077, Mayes County
Solar
125 MWAgreement signed Mayes, OKSPP May 20172025
Shaw Solar
Solar · Rio Lago Solar, LLC
125 MWAgreement signed Bandera, TXERCOT Oct 2020target 2026
Battery storage project GEN-2023-SR22, Mayes County
Battery storage
125 MWIn study Mayes, OKSPP Jun 20232024
Solar project GEN-2017-071, Payne County
Solar
125 MWAgreement signed Payne, OKSPP May 20172025
Page 109 of 184

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)