United States › Grid › Interconnection queues › New York

BATTERY STORAGE · NYISO

East Setauket Energy Storage

East Setauket Energy Storage is a 125 MW battery storage request in interconnection study in the NYISO interconnection queue, in Suffolk County, New York, connecting to LIPA.

Queue statusIn planning
  1. PlanningQueued Jan 2020 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Apr 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
971
Grid region
NYISO (New York)
Utility / transmission owner
LIPA
Developer
East Setauket Energy Storage, LLC
Connection point (POI)
Holbrook - Miller Place 138kV
Location
Suffolk County, New York
Technology
Battery: 125 MW
Total requested
125 MW
Study phase
FS
Queue status
Active
Entered queue
10 January 2020
Proposed online date
April 2027

Location

Marker shows the centre of Suffolk County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Suffolk County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem