BATTERY STORAGE · NYISO

Edwards Calverton Battery Storage

Edwards Calverton Battery Storage is a 60.0 MW battery storage request in interconnection study in the NYISO interconnection queue, in Suffolk County, New York, connecting to LIPA.

Queue statusIn planning
  1. PlanningQueued Sep 2021 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
1257
Grid region
NYISO (New York)
Utility / transmission owner
LIPA
Developer
Edwards Calverton Battery Storage
Connection point (POI)
Edwards Avenue Substation at 138 kV
Location
Suffolk County, New York
Technology
Battery: 60.0 MW
Total requested
60.0 MW
Study phase
SRIS, FS
Queue status
Active
Entered queue
22 September 2021
Proposed online date
March 2026

Location

Marker shows the centre of Suffolk County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Suffolk County