United States › Grid › Interconnection queues › Oklahoma

BATTERY STORAGE · SPP

Battery storage project GEN-2023-SR22, Mayes County

Battery storage project GEN-2023-SR22, Mayes County is a 125 MW battery storage request in interconnection study in the SPP interconnection queue, in Mayes County, Oklahoma, connecting to AEP.

Queue statusIn planning
  1. PlanningQueued Jun 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingDec 2024 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GEN-2023-SR22
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
AEP
Connection point (POI)
Explorer Claremore Tap COOYYAH4
Location
Mayes County, Oklahoma
Technology
Battery: 125 MW
Total requested
125 MW
Service type
Energy only (ERIS)
Study phase
IA PENDING
Queue status
Active
Entered queue
20 June 2023
Proposed online date
December 2024
Came online
December 2024

Location

Marker shows the centre of Mayes County; the queue data does not give exact sites.

Power plants in Oklahoma · Transmission lines in Oklahoma

Other requests in Mayes County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem