🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Montana

ONSHORE WIND · SPP

Onshore wind project GEN-2018-069, Wibaux County

Onshore wind project GEN-2018-069, Wibaux County is a 125 MW onshore wind request with a signed interconnection agreement in the SPP interconnection queue, in Wibaux County, Montana, connecting to WAPA.

Queue statusConsented
  1. PlanningQueued Oct 2018 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2031 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2018-069
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
WAPA
Connection point (POI)
WAPA-UGP Mingusville 230kV
Location
Wibaux County, Montana
Technology
Wind: 125 MW
Total requested
125 MW
Service type
NRIS and ERIS
Study phase
IA FULLY EXECUTED/ON SCHEDULE
Queue status
Active
Entered queue
26 October 2018
Proposed online date
December 2031

Location

Marker shows the centre of Wibaux County; the queue data does not give exact sites.

Power plants in Montana · Transmission lines in Montana

Other requests in Wibaux County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem