Onshore wind project GEN-2015-098, Wibaux County

Onshore wind project GEN-2015-098, Wibaux County is a 100 MW onshore wind request withdrawn in the SPP interconnection queue, in Wibaux County, Montana, connecting to WAPA.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2015 (completed)
  2. Withdrawn / abandonedMar 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2015-098
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
WAPA
Connection point (POI)
Dawson-Medora (Mingusville) 230kV
Location
Wibaux County, Montana
Technology
Wind: 100 MW
Total requested
100 MW
Service type
Energy only (ERIS)
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
23 October 2015
Proposed online date
December 2017
Withdrawn
March 2019

Location

Marker shows the centre of Wibaux County; the queue data does not give exact sites.

Power plants in Montana Β· Transmission lines in Montana

Other requests in Wibaux County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem