United States βΊ Grid βΊ Interconnection queues βΊ Montana
BATTERY STORAGE Β· SPPBattery storage project GEN-2019-024, Wibaux County
Battery storage project GEN-2019-024, Wibaux County is a 50.0 MW battery storage request withdrawn in the SPP interconnection queue, in Wibaux County, Montana, connecting to BEPC.
Queue statusWithdrawn / abandoned
- PlanningQueued May 2019 (completed)
- Withdrawn / abandonedMay 2022 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2019-024
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- BEPC
- Connection point (POI)
- Beaver Hill Sub
- Location
- Wibaux County, Montana
- Technology
- Battery: 50.0 MW
- Total requested
- 50.0 MW
- Service type
- NRIS and ERIS
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 8 May 2019
- Proposed online date
- December 2023
- Withdrawn
- May 2022
Location
Marker shows the centre of Wibaux County; the queue data does not give exact sites.
Other requests in Wibaux County
- Onshore wind project GEN-2018-069, Wibaux CountyOnshore wind Β· 125 MW Β· agreement signed
- Wind + storage project GEN-2019-023, Wibaux CountyWind + storage Β· 110 MW Β· agreement signed
- Onshore wind project GI-1506, Wibaux CountyOnshore wind Β· 100 MW Β· in study
- Onshore wind project GEN-2015-098, Wibaux CountyOnshore wind Β· 100 MW Β· withdrawn
- Onshore wind project G994, Wibaux CountyOnshore wind Β· 19.5 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem