Baldy Mesa 2

Baldy Mesa 2 is a 125 MW solar + storage request with a signed interconnection agreement in the CAISO interconnection queue, in San Bernardino County, California, connecting to SCE.

Queue statusConsented
  1. PlanningQueued Apr 2018 (completed)
  2. ConsentedApr 2021 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Nov 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
1519
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Roadway Substation 115kV
Location
San Bernardino County, California
Technology
Solar: 50.0 MW · Battery: 75.0 MW
Total requested
125 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Active
Entered queue
16 April 2018
Agreement signed
5 April 2021
Proposed online date
November 2026

Location

Marker shows the centre of San Bernardino County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in San Bernardino County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem