🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Indiana

SOLAR · PJM

Bluestem Solar

Bluestem Solar is a 125 MW solar request with a signed interconnection agreement in the PJM interconnection queue, in Laporte County, Indiana, connecting to AEP.

Queue statusConsented
  1. PlanningQueued Mar 2020 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
AF2-359
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Olive-University Park 345 kV
Location
Laporte County, Indiana
Technology
Solar: 125 MW
Total requested
125 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Active
Entered queue
31 March 2020
Proposed online date
December 2027

Location

Marker shows the centre of Laporte County; the queue data does not give exact sites.

Power plants in Indiana · Transmission lines in Indiana

Other requests in Laporte County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem