SOLAR · PJMQuarter Horse Solar
Quarter Horse Solar is a 125 MW solar request with a signed interconnection agreement in the PJM interconnection queue, in Charlotte County, Virginia, connecting to Dominion.
Queue statusConsented
- PlanningQueued Sep 2020 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Mar 2031 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- AG1-285
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- Dominion
- Developer
- Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
- Connection point (POI)
- Chase City-Central 115 kV
- Location
- Charlotte County, Virginia
- Technology
- Solar: 125 MW
- Total requested
- 125 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study; Interim/Interconnection Service Agreement: Document Posted
- Queue status
- Active
- Entered queue
- 28 September 2020
- Proposed online date
- March 2031
Location
Marker shows the centre of Charlotte County; the queue data does not give exact sites.
Other requests in Charlotte County
- Solar project AG2-077, Charlotte CountySolar · 200 MW · in study
- Courthouse SolarSolar · 167 MW · in study
- Solar project AG2-442, Charlotte CountySolar · 140 MW · in study
- Solar project AG2-441, Charlotte CountySolar · 113 MW · in study
- Solar project AH2-078, Charlotte CountySolar · 99.7 MW · in study
- Solar project AG2-440, Charlotte CountySolar · 75.0 MW · in study
- Solar project AI2-224, Charlotte CountySolar · 55.0 MW · in study
- Twittys Creek SolarSolar · 13.8 MW · built
- Solar project AG1-181, Charlotte CountySolar · 150 MW · withdrawn
- Solar project AD2-063, Charlotte CountySolar · 150 MW · withdrawn
- Solar project AF1-246, Charlotte CountySolar · 100 MW · withdrawn
- Solar project AH2-079, Charlotte CountySolar · 69.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem