🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

BATTERY STORAGE · ERCOT

Prairie Blossom Storage

Prairie Blossom Storage is a 123 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Howard County, Texas.

Queue statusIn planning
  1. PlanningQueued Dec 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
27INR0323
Grid region
ERCOT (Texas)
Developer
Prairie Blossom Storage, LLC
Connection point (POI)
1322 Big Spring 138kV
Location
Howard County, Texas
Technology
Battery: 123 MW
Total requested
123 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
19 December 2024
Proposed online date
September 2028

Location

Marker shows the centre of Howard County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Howard County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem